Project Name: West Angelas Deposit B - Earthworks, Roadworks, Civil and Miscellaneous Works
Client: Rio Tinto
Project Commencement Date: February 2014
Project Completion Date: December 2014
EPCM: Calibre
Project Location: Newman, WA
West Angelas Deposit B
Key Facts
Number of staff at peak: 85
Volume of concrete: 2,000m³
Volume of earthwork: 60,000m³
Tonnes of REO: 200
Project Overview
The West Angelas Deposit B (WADB) Project provides expansion by 6Mtpa to provide a 35Mtpa saleable ore product mine facility. The WADB Project includes the design and construction of a new haul road, diversion berm and diversion channel at Deposit B and associated infrastructure and plant upgrades at Deposit A to provide the increased mine production.
The site is located at the West Angelas Mine facility in Western Australia. It is approximately 125km North West of Newman, and approximately 1000km north of Perth by road in the West Pilbara region of North Western Australia.
Project Scope of Works
Construction consists of:
Foundation and subgrade preparation
Screening, sorting selection loading and hauling of materials
Earthworks and capping works for: EPCM laydown pads, CO51, CO52 and C009 modifications and extensions, stacker transportation road and erection and deconstruction pads, ST03 trackwork earthworks and temporary tie down works, TS51, TS52 and Sample Station pads, communications tower pad capping works
Supply and installation of drainage culverts including inlet and outlet structures for: WADB haul road, Deposit B LV access road and Deposit A plant area
Erosion protection works for: WADB haul road, Deposit B LV access road and Deposit A plant area
Construction of concrete foundation systems including footings, slabs and other general associated concrete items for: FEL Hopper BN201, CO51, CO52, CO09, TS51, TS52, Sampling Facility and Laboratory, electrical substations 1 and 2, finger stockpile lighting towers and communication tower
Construction of foundation system and concrete retaining structures for FEL Hopper BN201
Detailed backfilling of concrete structures for: FEL Hopper BN201 and retaining wall, CO51, CO52, CO09, TS51, TS52, Sampling Facility and Laboratory, electrical substations 1 and 2, finger stockpile lighting towers and communication tower
Concrete supply and mix design
Removal and modification of existing concrete foundations and slabs affected by the proposed works
Installation of new ST03 machine rail strip footings, trackwork, new turn-around pit, end of travel buffers, jacking pads, dead end box and boom tie down
Miscellaneous foundations, footings, slabs and other associated concrete items
Temporary works
Removal ST03 erection and deconstruction pads and temporary access road on completion of Stacker erection and deconstruction