Client: Rio Tinto 
Dates: Mar 21 – Current
Scope of Contract: Design and construct – In-Pit Support Facilities

Client: Rio Tinto 
Dates: Sep 20 – Oct 20
Scope of Contract: ROM slope erosion works

Client: Rio Tinto / Lorrex Contracting
Dates: Aug 19 – Jun 20 
Scope of Contract: Mine Plant Access Roads

Client: Rio Tinto
Dates: Jul 19 – Dec 20
Concrete: Circa 28,000 m3
Scope of Contract: Concrete Works & Underground Services for the Process Plant

Client: Albemarle
Dates: Jun 19 – Aug 20 
Concrete: Circa 30,000 m3
Scope of Contract: Detailed Earthworks & Concrete for the Pyromet Circuit.

Client: BHP
Dates: May 19 – Jan 20 
Scope of Contract: Misc. Works including Civil, Building, Electrical & Plumbing to BHP Mulla Mulla Village Expansion including Finishing Works.

Client: BHP
Dates: Apr 19 – Mar 20

Client: BHP
Dates: Jan 19 – May 19
Concrete: 1,500 m3
Scope of Contract: Detailed Earthworks & Concrete including underground services for the Kwinana Nickel Sulphate Plant.

Client: Pilbara Minerals
Dates: Jan 19 – Mar 19
Scope of Contract: Misc. Service Contract.

Client: FMG
Dates: Dec 18 – Jan 19
Scope of Contract: Misc. Earthworks and Roadworks including Sedimentation Pond.

Client: BHP
Dates: Nov 18 – Feb 19
Scope of Contract: Installation Of Transportable Office Facility including Services and Commissioning.

Client: BHP
Dates: Nov 18 – Mar 19

Client: BHP
Dates: Sept 18 – Feb 19
Scope of Contract: Roadworks and Asphalt to mitigate Dust within Operating Plant

Client: Mt Gibson Iron
Dates: Aug 17 – Jun 18
Scope of Contract:Misc. Works Contract

Client: BHP
Dates: Jun 18 – Oct 18
Scope of Contract: Supply and install pipework coming from the Waste Water Treatment Plant to the spray field and commission

Client: BHP
Dates: Mar 18 – Aug 18
Scope of Contract: Design & Construct of Mine Access Road including all Asphalt, Signage, line marking and barriers.

Client: BHP
Dates: Feb 18 – Sept 18
Scope of Contract: Design & Construct of Dome Shelter

Client: BHP
Dates: Jan 18 – Jan 18
Scope of Contract: The biopile field trial is to optimise biopile remediation for WB24 & WB25 Rail Loop Pond contaminated soil

Client: BHP
Dates: Jan 18 – Sept 18
Scope of Contract:Road upgrades to OHP 1 & OHP 2 including asphalt resurfacing

Client: Dacian Gold GR Engineering
Dates: May 17 – Nov 17
Concrete: 4,100 m3
Scope of Contract: Civil Construction

Client: BHP
Dates: Apr 17 – Oct 17
Scope of Contract: Deconstruction of four construction camps – Turner River, Cowra, Jinidi & Marillana

Client: BHP
Dates: Apr 17 – Oct 17
Scope of Contract: Road upgrades including asphalt resurfacing

Client: Rio Tinto / RCR
Dates: Feb 17 – Sept 17
Concrete: 5,000 m3
Scope of Contract: Bulk earthworks and civils for the SGE primary crushing, OLC and 33kV distribution project

Client: Rio Tinto / Calibre
Dates: Jun 16 – Nov 16
Earthworks: 47,060 m3
Scope of Contract: Misc. Earthworks

Client: BHP
Dates: Feb 16 – Jan 17
Scope of Contract: Upgrade Kitchen Mess and Accommodation Village

Client: Rio Tinto
Dates: Oct 15 – May 16
Concrete: 4,089 m3
Scope of Contract: Power station civil works

Client: Sirius Gold Pty Ltd / GR Engineering
Dates: Sept 15 – Mar 16
Concrete: 5,500 m3
Scope of Contract: Civil works

Client: Alcoa / Sedgman
Dates: Feb 15 – Jun 15
Concrete: 2,483 m3
Scope of Contract: Filtration Facility – Civil Works

Client: Rio Tinto / Calibre
Dates: Oct 14 – Feb 15
Scope of Contract: Design and Construct Raw / Fire Water

Client: Rio Tinto 
Dates: Sept 14 – Aug 15
Scope of Contract: Upgrade Existing – Civil Works

Client: Rio Tinto / RCR
Dates: Jun 14 – Dec 14
Earthworks: 26,000 m3
Scope of Contract: ROM Wall – Civil works

Client: FMG – Iron Bridge
Dates: May 14 – Sept 14
Concrete: 5,000 m3
Scope of Contract: Civil works

Client: BHP Billiton / Worley Parsons
Dates: May 13 – Jul 14
Scope of Contract: Design & Construct Water Treatment Plant

Client: BHP Billiton / Worley Parsons
Dates: Aug 12 – Apr 13
Concrete: 8,189 m3
Scope of Contract: Power Station Civil Works

Client: Rio Tinto / SKM
Dates: Aug 12 – Nov 14
Concrete: 67,000 m3
Scope of Contract: The scope includes the concrete structures and earthworks associated with Car Dumper 6/7 and the Stockyard for the Cape Lambert Port B (353MTPA) Project. The project will include more than 67,000m3 of concrete and 400,000m3 of earthworks

Client: BHP Billiton / Fast JV
Dates: Jul 12 – Apr 13
Concrete: 6,800 m3
Scope of Contract: Concrete and detailed earthworks for the Train Loadout Facility

Client: BHP Billiton / Fast JV
Dates: Jul 12 – Dec 13
Concrete: 3,300 m3
Scope of Contract: Concrete and detailed earthworks for the blending yards at Nelson Point and Finucane Island as part of the Port Hedland Inner Harbour Project

Client: BHP Billiton / Fast JV
Dates: Jun 12 – Apr 13
Concrete: 4,474 m3
Scope of Contract: Concrete and detailed earthworks associated for the construction of the Train Load Out Tunnel

Client: Rio Tinto / SKM
Dates: Mar 12 – Mar 13
Concrete: 24,500 m3
Scope of Contract: Stockyard Civil Works Package 2 for the Cape Lambert Port B (283MTPA) Project. The scope included more than 24,500m3 of concrete and 35,000m3 of earthworks. 

Client: BHP Billiton / Fast JV
Dates: Jan 12 – Apr 12
Concrete: 600 m3
Scope of Contract: Power distribution substation, including all civil and electro- structural works

Client: Rio Tinto / SKM
Dates: Aug 11 – Sept 12
Concrete: 20,000 m3
Scope of Contract: Civil works for the Cape Lambert Port B (283MTPA) Project which included Car Dumper 5, Screenhouse and the 33kV Power Pole Foundations. The project included more than 20,000m3 of concrete and over 200,000m3 of earthworks.

Client: BHP Billiton / Fast JV
Dates: Jul 11 – Aug 12
Concrete: 5,500 m3
Scope of Contract: Concrete & detailed earthworks associated with CD5 including backfill of 140,000m3 earthworks

Client: BHP Billiton / Fast JV
Dates: May 11 – Jun 12
Concrete: 6,700 m3
Scope of Contract: Concrete and detailed earthworks associated with North Yard routes upgrade, South Yard and upgrade routes, and South Berths E & F conveyor/transfer station infrastructure at Nelson Point. Also the Concrete and detailed earthworks associated with conveyor/transfer station infrastructure at Finucane Island.

Client: Citic Pacific Mining MCC Mining
Dates: Feb 11 – Oct 11
Concrete: 14,000 m3
Scope of Contract: The tailing thickener included rock excavation (drill and blast), earthworks (200,000m3) in addition to the tailing thickener concrete installation

Client: Citic Pacific Mining MCC Mining
Dates: Oct 09 – Sept 10
Concrete: 42,000 m3
Scope of Contract: The ball mill installation works comprised of concrete works for six near identical concentrator process plant lines which consisted of the primary and secondary magnetic separation process plants and ball mill foundations

Client: Rio Tinto / Calibre
Dates: Oct 08 – Nov 09
Concrete: 8,500 m3
Scope of Contract: Concrete & Civil Works for process plant including Crusher and Train Loadout

Client: BHP Billiton / Fast JV
Dates: Mar 08 – Dec 08
Concrete: 6,000 m3
Scope of Contract: Various Concrete for port expansion project – including reclaimer / stacker

Client: BHP / MPDJV
Dates: Nov 07 – Jan 10
Concrete: 26,000 m3
Scope of Contract: Concrete & Civil Works for Car Dumper and Train Loadout.

Client: FMG
Dates: Apr 07 – Apr 08
Concrete: 24,000 m3
Scope of Contract: Concrete installation for various structures including crusher, screening, conveyor lines and reclaim vaults.

Client: Newmont Mining
Dates: Mar 07 – Mar 08
Concrete: 7,000 m3
Scope of Contract: Concrete and civil works for crusher

Client: BHP Billiton / Fast JV
Dates: Feb 07 – Jan 08
Concrete: 5,000 m3
Scope of Contract: Port Expansion – concrete works upgrades

Client: Rio Tinto / SKM
Dates: Jan 06
Scope of Contract: Port upgrade – construction of car dumper 4 and port facilities including stacker reclaimers

Client: Rio Tinto / SKM
Dates: Mar 05
Scope of Contract: Port upgrade – construction of car dumper and screeening building

Client: BHP Billiton / MPDJV
Dates: Jan 05 – Nov 05
Concrete: 7,500 m3
Scope of Contract: Concrete & Civil Works for process plant including ROM pad, Crusher and Train Loadout